The building remains at your disposal free of charge
With the construction lease, the building, financed by IRISOLARIS, remains at your disposal free of charge thanks to its rental:
IRISOLARIS is responsible for obtaining the building permit
You are leasing your land through a 30-year construction lease


IRISOLARIS finances the building (which it owns for the duration of the construction lease)
Our constructor partner carries out the construction
of the building and IRISOLARIS takes care of the installation of the photovoltaic power plant

Estimated time for
the finalization of the project:
12 months
Project timeline
1
Contact
Presentation of offers
and choice of solution
2 weeks

3
Project conception
Realization of the building permit
PC depot in town hall
Three weeks
2
Project validation
Productivity and connection studies
Signing of the promise to lease
2 weeks

5
Connection studies
Submission of the connection request
Obtaining the Purchase Price
Validation of connection conditions
4 months

6
Works and commissioning
Material selection and order
Execution of works
Commissioning of the plant
6 to 12 months

Planning authorization agreement
Instruction of building permit
Obtaining the order
Purge of building permit
3 months
4